Which type of demand response program is considered acceptable?

  1. Manual

  2. Semi-automated

  3. Fully automated

  4. Both semi-automated and automated

The correct answer is: Both semi-automated and automated

Demand response programs are crucial in managing electricity usage and ensuring grid stability, especially during peak demand times. Among the listed options, both semi-automated and fully automated programs are seen as acceptable because they promote efficient energy usage without requiring constant manual intervention. Semi-automated programs involve some level of automation while still allowing for human oversight or manual control. They serve as a middle ground, allowing operators to manage energy consumption effectively while being flexible and responsive to immediate needs. Fully automated programs, on the other hand, operate independently to adjust energy usage based on predefined criteria or real-time signals from the grid. This type of program is ideal for maximizing efficiency and responsiveness during peak periods, as they can react swiftly to changing grid conditions. Incorporating both semi-automated and fully automated demand response programs in building design and operation is aligned with LEED principles that advocate for sustainability and responsible resource management. This flexibility in demand response methods can significantly contribute to energy conservation efforts, making them an effective choice for achieving sustainability certification.